Milkymist One run 1 schedule
From Qi-Hardware
This page keeps track of the road to manufacturing the Milkymist One Boards.
[edit] Hardware
| Item | Description | Planned Start date | Status |
|---|---|---|---|
| Schematics | Schematics Released about Milkymist One by Sebastien | Done | |
| BOM | Parts List released by Sebastien | Done | |
| Schematics Reviewing | Collects Comments from Milkymist Developement list | Done | |
| Part Sourcing | Surveying and Quoting | Done | |
| Parts Ordered | Order Status | Feb. 26 | Done |
| Footprint Review | March 18 | Done | |
| Layout Criteria Preparation | Criteria for Key Parts Layout and others | Feb. 22 | Done |
| Placement for Layout | Place Key Parts | March. 27 | Done |
| PCB Layout Files Review | Review Routed Folder/Files, layout notes could be recorded in this stage | April 16 | Done |
| Generate Gerber/Drill Files | May 19 | Done | |
| Gerber/Drill Files Review | Review those files for SMT/DIP process | May 19 | Done |
| Gerber-Out to PCB maker | Checklist file, Start Producing PCBs | May 19 | Done |
| AI File Generation | For SMT process | May 19 | Done |
| PCB Back Check | Confirm PCB quality | ETA May 31 | Done |
| Stencil Making | For SMT solder paste process used by stencil file sent out | May 31 | Done |
| SMT & DIP Process | Process in Manufacturer | June 8 | Done |
| X-Ray Inspection | BGA soldering check | June 14 | Done |
| Test | Easy Power Voltage & Signals check | June 14 | Done |
[edit] Software
For more software details, please subscribe Milkymist-devel mailing list or joining this community.